Following the issue of the last Newsletter, works on site continue to progress well and you may have noticed we have now completed the 1st Floor Concrete Slab. Behind this we are progressing with the concrete columns and shear walls allowing the formation of the 2nd floor transfer slab in readiness for the metsec frame structure for the upper 5 floors. Over the course of next month the following activities will be undertaken: –

  • Continuation with the formation of columns from 1st to 2nd floor
  • Continuation with the Second Floor Concrete Slab n Installation of ducts for the services infrastructure. n Commencement of Sub-structure blockworks
  • Striking and Clearing away the temporary propping and shuttering.
  • We will continue to work on Saturdays from 8am –1pm. It is anticipated that Saturday working will cease at the End of May however if there is a change to this, we will advise you accordingly.

The Project Team

Alex Elliott – Senior Site Manager:
07918674049
aelliott@barnesconstruction.co.uk

Kevin Tyrrell – Senior Contracts Manager:
01473 322504
Ktyrrell@barnesconstruction.co.uk

Matthew McLaughlin – Senior Quantity Surveyor:
01473 272222
mmclaughlin@barnesconstruction.co.uk

Thank you for taking the time to read this newsletter

Regards
Alex Elliott

Barnes Construction

Who are we?

Barnes Construction operates throughout the country and this project is being managed and delivered out of the Ipswich Head Office.

To find out more information about Barnes Construction, please visit our website:

www.barnesconstruction.co.uk


How to contact us

Our nominated contact:

Alex Elliott: – 07918674049
aelliott@barnesconstruction.co.uk

Alex can be contacted during normal working hours.


Write to us

Alternatively, you can write to us at our office:

Barnes Construction
6 Bermuda Road
Ransomes Europark
Ipswich
Suffolk IP3 9RU


Working Hours

Our normal working hours are:

Monday to Friday – 07:00 to 17:00
Saturdays – 08:00 to 13:00
Sundays & Bank Holidays – nonworking


Deliveries and site traffic

We will ensure that all deliveries to site are properly planned and coordinated to minimise disruption. We aim to work to co-ordinate these with everyone to minimise disruption to everyone.