Hello from the Site Team For The New Travelodge in Wimbledon
Thank you for taking the time to read the 4th addition of our Newsletter. Since the last update works have progressed well and you will have seen the site changing over the last few weeks with the completion of the demolition works. The works completed during the last period were:
- Demolition
- Reduced level excavation for the piling matt
- Installation of piling matt
- Closure of Graham road and establishment of BC Welfare Facilities
- Erection of Site security Hoarding
Upcoming Works
- Continuation of Piling
- Commencement of on Site Drainage Works
- Closure of Beulah Road Footpath— This will be closed from the 27th of October, there will be an alternative footpath established in Beulah Road to maintain safe access for Pedestrians.
- Commencement of Ground Beams and Piling Caps
Reduced Level Dig
Piling Matt Install
Piling Works
Welfare & Site Security Fencing
The Project Team
Alex Elliott – Senior Site Manager:
07918674049
aelliott@barnesconstruction.co.uk
Kevin Tyrrell – Senior Contracts Manager:
01473 322504
Ktyrrell@barnesconstruction.co.uk
Matthew McLaughlin – Senior Quantity Surveyor:
01473 272222
mmclaughlin@barnesconstruction.co.uk
Thank you for taking the time to read this newsletter
Regards
Alex Elliott
Who are we?
Barnes Construction operates throughout the country and this project is being managed and delivered out of the Ipswich Head Office.
To find out more information about Barnes Construction, please visit our website:
How to contact us
Our nominated contact:
Alex Elliott: – 07918674049
aelliott@barnesconstruction.co.uk
Alex can be contacted during normal working hours.
Write to us
Alternatively, you can write to us at our office:
Barnes Construction
6 Bermuda Road
Ransomes Europark
Ipswich
Suffolk IP3 9RU
Working Hours
Our normal working hours are:
Monday to Friday – 07:00 to 17:00
Saturdays – 08:00 to 13:00
Sundays & Bank Holidays – nonworking
Deliveries and site traffic
We will ensure that all deliveries to site are properly planned and coordinated to minimise disruption. We aim to work to co-ordinate these with everyone to minimise disruption to everyone.